Dubai Municipality completes 90% of Deep Tunnel Drainage Project

004 scaled

Dawoud Al Hajri, Director General of Dubai Municipality said that the Municipality has completed close to 90% of the Deep Tunnel Drainage Project and the work continues without interruption, according to the scheduled time plan.

“The tunnel work was not affected during the exceptional national sterilization period and the fourth and final stage of tunnel excavation has been completed,” said Al Hajri.

“With this the tunnel project is entering the final point at the Artificial Island near the Jebel Ali port, after passing down from Sheikh Zayed Road, and the length of drilling for this stage reached 2.5 km. This brings the project to the end of the deep tunneling stage, with a length of 10.3 km,” he said.

“The first stage was completed on September 25, 2019. Thus, the tunnel has become ready for linkage and high operation in October 2020,” Al Hajri added.

“Pouring of 66,000 cubic meters of concrete for the main pumping station has been completed using 12,000 tons of reinforced steel, which will be able to absorb 110 cubic meters of water per second, equivalent to discharging 9.5 million cubic meters per day,” he said.