Project Location

Dubai Land

Project Details

​Project Objective:
establishment of a huge sports complex, its length is 200 meters, a width of 120 meters and height of 33 meters The capacity of 15,000 spectators and is unique being closed athlete building with air conditioning and is considered an environmentally friendly building.The project included a range of new technologies that rarely meet in one project.  Starting from the structure and diversify uses of controlled mechanically in the dimensions of swimming pools in length and depth.  In addition of that, the unique cover that covers those pools for non-water sports, moreover, the new lighting techniques and uniqueness in the displaying and facilities radio and television and control technology in temperature and humidity different in one space.
And ending with those have contributed as much as unprecedented in the saving of energy and water, which achieve savings in energy consumption of 7.94 MW / h which is 68% compared to the traditional system, translated financially to 34.44 million AED of the initial cost, and 12.74 million AED annual savings in addition to protecting environment of CO2 gas emissions by 5.2 tons / hour in the water, realizing a savings of 377.4 cubic meters / day, equivalent to 1.388 million AED / year.
It was cost control through applying of value engineering which led to the saving of 263 million AED by 22% of the total contract value.
Project elements:

The project consists of a main building as well as building energy as follows:
  • Main Building: (four floors) includes the main hall and includes 15,000 seats for spectators, and three swimming pools for swimming competitions, diving, and training provided with mobile floor for various training purposes. Also there is a VIP entrance, public entrance, Fina offices, businessmen compartments hospitality areas, cafeteria, media center, as well as services allocated to each floor.
  • Energy Center consists of pumps rooms, water tanks and filtration systems, electromechanical equipment and chillers.
  • General site work and infrastructure and landscape work.
Built-up area: 49,000 square meters

End User: Dubai Sports Council

 Project Completion Date

2010

  Project Expected Completion Date

 

 Video Gallery

  • Barca

  Photo Gallery

Hamdan   
Hamdan   
Hamdan   
Hamdan   
Hamdan